Tag Archives: Project Updates

Aquarius 40 Years ReCertification Travails – June 2018

Aquarius 40 Years ReCertification Travails June 2018 The 40 Year Recertification work at Aquarius has 2 main components: (1) Concrete Work of Towers and East Deck.  There are two other items provisioned by the Special Assessment 2017: (1) Elevators renewal … Continue reading

Posted in Construction & 40 Year Inspection, Pictures | Tagged , , , , , , , , , , , | Leave a comment

Aquarius East Pool Deck Construction Schedule Rev.: 2017/11/01

Aquarius East Pool Deck Construction Schedule Rev.: 2017/11/01 40 Year Re-Certification Exercise Follow the construction progress with the periodic revised schedules. Printer friendly file format of the East Pool Deck Schedule   2017/11/01        2017 11 01 E Deck … Continue reading

Posted in Construction & 40 Year Inspection | Tagged , , , , , , , , , | Leave a comment

40 Year Re-Certification Project Schedules

40 Year Re-Certification Project Schedules   The major initiative in the 40 Year Re Certification Exercise of Aquarius is the concrete work that embodies balconies, East side garage and deck including a new pool. The 40 Year Re-Certification also contemplates … Continue reading

Posted in Construction & 40 Year Inspection | Tagged , , , , , , , , , , , , , | Leave a comment

Aquarius New Stairs to the Hollywood Beach

Aquarius New Stairs to the Hollywood Beach  –   Preliminary Proposal This is first cut to the proposed new stairs from the East Pool Deck to the  sea-shore. The idea is to offer a more comfortable access to the beach from the … Continue reading

Posted in Amenities, Construction & 40 Year Inspection, Pictures | Tagged , , , , , , , , , , , , | Leave a comment

No stairs Aquarius Beach Access: Now it is for real

No stairs Aquarius Beach Access: Now it is for real   The wait is over. The Aquarius “stair less” access is ready. At the latest is will open Wednesday June 7. It may be operational tomorrow Tuesday June 6. This … Continue reading

Posted in Amenities, Construction & 40 Year Inspection, Pictures | Tagged , , , , , , , | Leave a comment

Aquarius Beach Access – NO STAIRS!

Aquarius Beach Access – NO MORE STAIRS!   With the construction project going on the Aquarius access to the Hollywood beach had to change. There was the need to find a temporary (hopefully permanent) alternative for the beach goers. At … Continue reading

Posted in Construction & 40 Year Inspection, Pictures | Tagged , , , , , , , | 1 Comment

Aquarius 40 Year Re Certification Project – 90 day Schedule

Aquarius 40 Year Re Certification Project – 90 day Schedule Preliminary Schedule subject to change ID Task Name Duration  Start Date 1 AQUARIUS CONDOMIINIUM 2 Contract Signed 0 days Mon 1/16/17 3 Master Restoration Permit Processing 66 days Tue 2/7/17 … Continue reading

Posted in Construction & 40 Year Inspection | Tagged , , , , | Leave a comment

The Aquarius 40 Re Years Cert. Starts – Pictures of the Construction Mobilization

The Aquarius 40 Years Re Certification Starts – Pictures of the Construction Mobilization The South Tower of the Aquarius Condominium is being prepared for the restoration. Swing stages, scaffolds, pedestrian protected pathways, new beach access are being built and installed … Continue reading

Posted in Construction & 40 Year Inspection, Pictures | Tagged , , , , , , , , , | Leave a comment

40 Year Re-Certification: Initial Building Permit APPROVED

40 Year Re-Certification: Initial Building Permit APPROVED May 9, 2017 It seems that now we can breathe more easily. The preliminary Building Permit has been approved by the City Of Hollywood. Now starts the count down of 80 weeks. There … Continue reading

Posted in Board of Directors, Construction & 40 Year Inspection | Tagged , , , , , , , , , | Leave a comment

Aquarius Membership Meeting April 6, 2017 – Material Alterations

Aquarius Membership Meeting April 6, 2017 – Material Alterations  the results are in: Owners of apartments at Aquarius Condominium had a formal Membership Meeting April 6th., 2017. The the quorum was of 174 owners counted either by proxy or physical … Continue reading

Posted in Amenities, Board of Directors, Construction & 40 Year Inspection, Pictures | Tagged , , , , , , , , , | Leave a comment