Tag Archives: Project Updates
Aquarius 40 Years ReCertification Travails – June 2018
Aquarius 40 Years ReCertification Travails June 2018 The 40 Year Recertification work at Aquarius has 2 main components: (1) Concrete Work of Towers and East Deck. There are two other items provisioned by the Special Assessment 2017: (1) Elevators renewal … Continue reading
Aquarius East Pool Deck Construction Schedule Rev.: 2017/11/01
Aquarius East Pool Deck Construction Schedule Rev.: 2017/11/01 40 Year Re-Certification Exercise Follow the construction progress with the periodic revised schedules. Printer friendly file format of the East Pool Deck Schedule 2017/11/01 2017 11 01 E Deck … Continue reading
40 Year Re-Certification Project Schedules
40 Year Re-Certification Project Schedules The major initiative in the 40 Year Re Certification Exercise of Aquarius is the concrete work that embodies balconies, East side garage and deck including a new pool. The 40 Year Re-Certification also contemplates … Continue reading
Aquarius New Stairs to the Hollywood Beach
Aquarius New Stairs to the Hollywood Beach – Preliminary Proposal This is first cut to the proposed new stairs from the East Pool Deck to the sea-shore. The idea is to offer a more comfortable access to the beach from the … Continue reading
No stairs Aquarius Beach Access: Now it is for real
No stairs Aquarius Beach Access: Now it is for real The wait is over. The Aquarius “stair less” access is ready. At the latest is will open Wednesday June 7. It may be operational tomorrow Tuesday June 6. This … Continue reading
Aquarius Beach Access – NO STAIRS!
Aquarius Beach Access – NO MORE STAIRS! With the construction project going on the Aquarius access to the Hollywood beach had to change. There was the need to find a temporary (hopefully permanent) alternative for the beach goers. At … Continue reading
Posted in Construction & 40 Year Inspection, Pictures
Tagged 2017, 40 year, 40 year recertification, beach, beach access, construction, Project, Project Updates
1 Comment
Aquarius 40 Year Re Certification Project – 90 day Schedule
Aquarius 40 Year Re Certification Project – 90 day Schedule Preliminary Schedule subject to change ID Task Name Duration Start Date 1 AQUARIUS CONDOMIINIUM 2 Contract Signed 0 days Mon 1/16/17 3 Master Restoration Permit Processing 66 days Tue 2/7/17 … Continue reading
The Aquarius 40 Re Years Cert. Starts – Pictures of the Construction Mobilization
The Aquarius 40 Years Re Certification Starts – Pictures of the Construction Mobilization The South Tower of the Aquarius Condominium is being prepared for the restoration. Swing stages, scaffolds, pedestrian protected pathways, new beach access are being built and installed … Continue reading
40 Year Re-Certification: Initial Building Permit APPROVED
40 Year Re-Certification: Initial Building Permit APPROVED May 9, 2017 It seems that now we can breathe more easily. The preliminary Building Permit has been approved by the City Of Hollywood. Now starts the count down of 80 weeks. There … Continue reading
Aquarius Membership Meeting April 6, 2017 – Material Alterations
Aquarius Membership Meeting April 6, 2017 – Material Alterations the results are in: Owners of apartments at Aquarius Condominium had a formal Membership Meeting April 6th., 2017. The the quorum was of 174 owners counted either by proxy or physical … Continue reading