Aquarius 40 Year Re Certification Project – 90 day Schedule

Aquarius 40 Year Re Certification Project – 90 day Schedule

Preliminary Schedule subject to change

ID Task Name Duration  Start Date
1 AQUARIUS CONDOMIINIUM
2 Contract Signed 0 days Mon 1/16/17
3 Master Restoration Permit Processing 66 days Tue 2/7/17
4 Mobilization 5 days Tue 5/16/17
5 Phase 1 – South Tower 81 days Tue 5/16/17
6 Balcony Access Equipment Installation 10 days Tue 5/16/17
7 Shutter Removal, Debris Chute, & Protection Install 20 days Wed 5/24/17
11 Balcony Demolition 40 days Thu 6/22/17
12 1st Floor Balcony Reconstruction 15 days Fri 8/18/17

 