Aquarius 40 Year Re Certification Project – 90 day Schedule
Preliminary Schedule subject to change
ID | Task Name | Duration | Start Date |
1 | AQUARIUS CONDOMIINIUM | ||
2 | Contract Signed | 0 days | Mon 1/16/17 |
3 | Master Restoration Permit Processing | 66 days | Tue 2/7/17 |
4 | Mobilization | 5 days | Tue 5/16/17 |
5 | Phase 1 – South Tower | 81 days | Tue 5/16/17 |
6 | Balcony Access Equipment Installation | 10 days | Tue 5/16/17 |
7 | Shutter Removal, Debris Chute, & Protection Install | 20 days | Wed 5/24/17 |
11 | Balcony Demolition | 40 days | Thu 6/22/17 |
12 | 1st Floor Balcony Reconstruction | 15 days | Fri 8/18/17 |
.o0o.