Daily Archives: May 31, 2017

Aquarius Beach Access – NO STAIRS!

Aquarius Beach Access – NO MORE STAIRS!   With the construction project going on the Aquarius access to the Hollywood beach had to change. There was the need to find a temporary (hopefully permanent) alternative for the beach goers. At … Continue reading

Posted in Construction & 40 Year Inspection, Pictures | Tagged , , , , , , , | 1 Comment

Aquarius 40 Year Re Certification Project – 90 day Schedule

Aquarius 40 Year Re Certification Project – 90 day Schedule Preliminary Schedule subject to change ID Task Name Duration ┬áStart Date 1 AQUARIUS CONDOMIINIUM 2 Contract Signed 0 days Mon 1/16/17 3 Master Restoration Permit Processing 66 days Tue 2/7/17 … Continue reading

Posted in Construction & 40 Year Inspection | Tagged , , , , | Leave a comment