ACG Engineering Report of 2014: Balconies, Beams, Columns of Aquarius

Logo black no lineACG Engineering Report of 2014 Balconies, Beams, Columns of Aquarius 

 

In September 30 2014 the Board of Directors received a report from ACG Engineering regarding the need to address issues on the Aquarius balconies, beams, columns and walls of both towers North and South.

This very basic report addressed aspects of concrete restoration exclusively. All other items such balconies railings and tiles were not included. Paint and the electrical aspects also were not included. The repair of the East Deck and the East pool were not in this estimate

At the end of the initial 7 pages report the preliminary estimated cost was of $ 2,151,004.00 (Building 1 (North)$ 978.937.00 plus Building 2 (South)  $ 1,172,067.00). It is important to mention that the rate of deterioration increases overtime. As it was noted before this evaluation was done 2 years ago.

Besides the this document that is attached to this post ACG produced a 2 volume binder with the assessment of the buildings balconies. This work is going to be used by the firm Hillman Engineering that is executing a complete investigation to address all items required by the 40 Year Re-certification exercise.

To better appreciate the ACG report (282 pages) please click the link bellow:  (all links open in a new tab)

        2014 09 Aquarius Balconies Survey C     

Please follow the instructions on the first page if you want go directly to see the specific status of your balcony in 2014. Of course the situation did not improve after 2 years of salt, sun, heat  and rain.

_________________________________________________

A comprehensive explanation of the Broward County 40 Year Building Safety Inspection Program may be seen here:

https://aquariusuno.com/2015/04/15/broward-county-40-year-building-safety-i-program/

A newer revision of this same document can be seen at the Broward County website:

Broward County 40 Year

.o0o.

 

 

Posted in Construction & 50 & 40 Year Recertifications | Tagged , , , , , , , | Leave a comment

Gentle Yoga with Julie June 2016

LOGO LADYWonderful “Gentle Yoga with Julie”

 

Classes began on June 22. It will be held every Wednesday night from    7-8 PM in the Green Room.

2016 yogaFor anyone who is interested – any level! We do great stretching and balancing.

Learn how to breathe and love your body. Come join us. Only $10 a class.

If you would like more information –  

call Roni at 954 929 5797      no reservation required

benefist.yoga

Posted in Amenities, Social | Tagged , , , , , | Leave a comment

Aquarius GYM Bathrooms Plans and Specifications June 2016

LOGO SILHOUETTEAquarius GYM Bathrooms Plans and Specifications

The bathrooms in the Gymnasium of Aquarius need refurbishing. Here are the plans reviewed by the Construction Committee and the Board of Directors. The condominium invites qualified contractors to submit proposals. 

The proposals should arrive before July 11, 2016 at the Aquarius Management Office.  2751 S Ocean Dr., Hollywood Fl.

Additional information with Mr. David Slavin, Property Manager  tel.: 954-921-7924

The plans are in .pdf file format

AQUARIUS BATHROOMS MATERIAL SUBMITTALS AND MANUAL

  1. AQUARIUS WOMEN BATHROOM SPECIFICATIONS
  2. M-1 Women’s Bathroom 6-1-16-M-1
  3. P-1 Women’s Bathroom 6-1-16
  4. WS-1 Women
  5. WS-1 Women
  6. WS-2 Women
  7. WS-3 Women
  8. WS-4 Women
  9. WS-5 Women

______________________________________

  1. AQUARIUS MEN BATHROOM SPECIFICATIONS
  2. E-1 Men’s Bathroom 6-1-16-E-1
  3. E-1 Men’s Bathroom 6-1-16-E-1
  4. M-1
  5. S-1 Men
  6. S-2 Men
  7. S-3 Men
  8. S-4 Men
  9. S-5 Men

 

Posted in Amenities, Construction & 50 & 40 Year Recertifications | Tagged , , , | Leave a comment

Hoisting New Central Air Cond. Components to the top of Aquarius June 20, 2016

This gallery contains 10 photos.

Hoisting New Central Air Cond. Components to the top of Aquarius  June 20, 2016 It was a short activity. By early morning the trucks arrived to the next door building The Residences of Hollywood. There was a truck with the … Continue reading

More Galleries | Tagged , , , , , , | Leave a comment

Large debris falling from 7th floor damages car June 18, 2016

LOGO BLUELarge debris falling from 7th floor damages car  June 18, 2016

 

Last week-end during strong rain and winds large pieces of mortar fell from the 7th floor of Aquarius North Tower. Fortunately no one was injured. A parked car had its windshield smashed. Had this large piece of mortar hit a person a serious injury or even worse could happen.

After 40 years of the construction of Aquarius it is imperative that complete inspection and repairs be made. Considering what happened it is important to address the structure of the building in a timely and effective maner.

No more procrastination. Immediate action is required.2016 06 18 Balcony falling apart2

Balcony on the 7th floor, North Tower, from where mortar fell.

2016 06 18 Car damaged by mortar

Rear windshield damaged by falling rock.

2016 06 18 Balcony mortar on the floor2

Several pieces of dangerous mortar spread out on the Valet Deck. Happily no person was walking by. No injuries to report at this time.

 

.o0o.

Posted in Construction & 50 & 40 Year Recertifications, Pictures | Tagged , , , , , , | Leave a comment

Aquarius 40 Year Recertification Preliminary Schedule

AQUARIUS-3D logoAquarius 40 Year Recertification  Preliminary Schedule

 

 

The 40 Recertification exercise of Aquarius has several phases.

The first one consisted of 6 presentations of engineering firms specialized in the assessment of multi store buildings needs to have a sound 40 year recertification in structural and electric areas.

The second phase was to select the firm to conduct the evaluation. In this phase Hillman Engineering was selected and presented the work schedule bellow. This second phase has an estimated time of completion of 201 days. For example if initiated June 9, 2016 it would be complete March 29, 2017.

The third phase will the hiring of a construction firm to conduct the repairs need to make Aquarius complaint with 40 Year Recertification requirements imposed by the Broaward County, Florida.

Construction Contract    201 Days  

ABOD = Aquarius Board,  AMGT = Aquarius Management, Hill = Hillman Engineering

 Task                                                                    Days     Responsibility

Evaluation Performed              33 days     

  • Parking Garage                                            10     Hill
  • Pool                                                                    2      Hill
  • Pool Deck                                                         5      Hill
  • Roof                                                                    1      Hill
  • Units/inc. Balconies                                  10      Hill
  • Electrical Evaluation                                  5       Hill

 Reports Produced                       24 days 

  • 40 Year Struc.  Compliance Report       5      Hill
  • 40 Year Elect. Compliance  Report        5      Hill
  • Detailed Evaluation Report                     15      Hill
  • Engineer’s Estimated Budget                  10     Hill

Design and Specifications       60 days   ABOD & Hill

Plans                                                60 days
Plans concurrent with Design

  • Finish Choices-e.g. Pavers                        20    Hill
  • Specifications                                                40     ABOD

Financing                                    60 days

  •  Meeting to Inform Residents                    1       AMGT
  • Notification of   Assessment Meeting    15      AMGT
  • Assessment BOD  Approval                         1      ABOD
  • Assessment Begins                                         0      AMGT
  • Solicit Banks                                                   10      AMGT
  • Terms Sheet                                                    40      AMGT
  • Get Credit Line                                                      ABOD & AMGT

Contractor Selection            93 days

  •  Board Approval to Bid Design                  5       ABOD, AMGT & Hill
  • Contractors Bid Work                                20      Hill & Contractor TBA
  • Spreadsheet Bids for Comparison           5       Hill
  • Qualify Bids                                                    10       Hill
  • Contractor Interviews                                  7        ABOD, AMGT & Hill
  • Board Votes (1st Choice)                             1        ABOD & AMGT
  • Draft Contract                                                15       AMGT
  • Finalize Schedule of Values                      15       Hill & Contractor TBA
  • Negotiate Contract                                       15        ABOD, AMGT & Contr. TBA
  • Mobilization                                                   10        ABOD, AMGT & Hill

.o0o.

 

Posted in Board of Directors, Construction & 50 & 40 Year Recertifications, Management Office | Tagged , , , , , , | Leave a comment

Is there a crane in Aquarius future?

Is there a crane in Aquarius future?

A new central Air Conditioning system is being installed at Aquarius. This system will Liebherr-MOBILE-CRANEprovide climate control for both Aquarius towers. It replace the old system and will provide fewer interruptions, more comfort in building hallways and less repairs.

20160529 crane 1

 

The replacement is a complex operation that will require a crane to place the heavy equipment in the top of both buildings. During this replacement the hallways will have no air conditioning. The air conditioning in individual apartments are not affected.

The work schedule is from June 13 to mid July. No air conditioning in the hallways should last for two weeks.

Vmech is the firm conducting the work.

The sacrifice is will pay of.

 

.o0o.

 

Posted in Construction & 50 & 40 Year Recertifications, Contracts | Leave a comment

Orlando: sad at sunrise June 12, 2016

Orlando: sad at sunrise     June 12, 2016

About 100 humans dead or hurt at Pulse Night Club, Orlando, Florida.

2016 03 12 Orlando sad

Orlando city of happiness is sad today.

Enough intolerance. Enough radicalism. Let’s stop hate!

Posted in News from Around and Beyond, Pictures | Tagged , , , , , | Leave a comment

Some New Some Old at Aquarius – June 2016

AQUARIUS-3D logoSome New Some Old at Aquarius –  June 2016

A pictorial display special for those that are up North.

20160604_154140

The Aquarius Community got two beautiful metal baskets to embellish the Lobby. Thank you very much Judy Ort.

Partial view of the new sofas, chairs and basket in the Aquarius Lobby.

Partial view of the new sofas, chairs and basket in the Aquarius Lobby.

New chairs, sofas, baskets in the Lobby. If you look hard enough you can see the mermaid. Fountains on the right side.

New chairs, sofas, baskets in the Lobby. If you look hard enough you can see the mermaid. Fountains on the right side.

The new library on the South Building. A very short low key campaign resulted in my books donated. The furniture is composed from chairs and tables that once were used in the Aquarius restaurant. When we find funds they will be replaced.

The new library on the South Building. A very short low key campaign resulted in my books donated. The furniture is composed from chairs and tables that once were used in the Aquarius restaurant. When we find funds they will be replaced.

The Library works in an honor systems. Bring one book take one book. Your donation is appreciated. We now have a UD 4K 75 inches TV set. The first show was a success. Did you come?

The Library works in an honor systems. Bring one book take one book. Your donation is appreciated. We now have a UD 4K 75 inches TV set. The first show was a success. Did you come?

A receiver previously used in the Cascade Room now gives theatrical sound for the new TV set in the Library.

A receiver previously used in the Cascade Room now gives generous theatrical sound for the new TV set in the Library.

A state of the art sound system is being installed in the Cascade Room. Similar scaled down sound system provides ambient music for Lobby, Bar, Aquarius Room and Hallway.

A state of the art sound system is being installed in the Cascade Room. Similar scaled down sound system provides ambient music for Lobby, Bar, Aquarius Room and Hallway.

20160603_170817

Billiards and Cards Room. Billiards tables got new covers. Some furniture from was brought from other locations. The result is maximum elegance with minimum investment. Yes, there is a ping-pong table available.

New shinny Valet Carts. After many, many years of good services the old carts needed retirement.

New shinny Valet Carts. After many, many years of good services the old carts needed retirement.

No doubt there still a lot to be done . Maybe the most important lesson is to try to keep all we have in its best shape. Let’s not leave anything is disrepair and let’s finish what remains to be done.

After all Aquarius is our home.

.o0o.o0o.

 

Posted in Amenities, Pictures | 1 Comment