Tag Archives: Entry Area
West Wall Repair and supporting documentation
West Wall Repair detail and supporting documentation August 8, 2015 The attached pdf file presents: West Wall Repair depiction June 4, 2015 CSI Contract Progress Report with authorization of work June 25, 2015 CSI Contract Progress Report July 23, … Continue reading
Posted in Construction & 50 & 40 Year Recertifications, Pictures
Tagged 2015, Entry Area, Main Entry, Project, Project Updates, West Deck, West Pool
Leave a comment
Phase 2 Ready for Concrete Restoration
Phase 2 of Concrete Restoration is almost ready for concrete pour Some news on the ongoing projects at Aquarius: – Gym expected to reopen mid July 2015, … Continue reading
Posted in Committees, Construction & 50 & 40 Year Recertifications
Tagged 2015, construction, Entry Area, Garage, Lobby, Meeting, Project, Project Updates, Renditions, West Deck
5 Comments
July 1st. New Installment of 2015 Special Assessment Due
July 1st. New Installment of 2015 Special Assessment Due Click here to see the amount due .o0o.o0o.
Posted in Construction & 50 & 40 Year Recertifications, Finance
Tagged 2015, assessment, capital, construction, Deck, Entry Area, finance, Garage, improvement, Lobby, Main Entry, West Deck, West Pool
Leave a comment
Sam Schmuter Responds to TV Channel 10 report June 24,2015
Response to TV Local Channel 10 by Samson Schmuter, 1101N, Aquariuscondo.net Webmaster June 24, 2015 →TRANSLATE THIS At the bottom of this post links to diverging and concurrent opinions on the … Continue reading
Posted in Construction & 50 & 40 Year Recertifications, Finance
Tagged 2015, assessment, Channel 10, construction, Deck, Entry Area, finance, Garage, Project, Project Updates, TV, Valet, West Deck, West Pool
Leave a comment
Construction Committee Update June 23, 2015
Construction Committee Update June 23, 2015 The purpose of this report is to provide Aquarius owners with the most recent status report concerning the current construction projects. This report is based on information available as of June 18, 2015. … Continue reading
A Letter from your Board of Directors – Aquarius
.A Letter from your Board of Directors June 17, 2015 Dear Aquarius Condominium Association Member: By now you have been contacted numerous times by a dissatisfied faction of unit owners seeking to obtain your … Continue reading
Lobby and Adjoining Areas Renovation Scope of Work June 11 2015
Lobby and Adjoining Areas INTERIOR RENOVATION – SCOPE OF WORK AQUARIUS CONDOMINIUM • 2751 S. OCEAN DRIVE, HOLLYWOOD, FL. AS OF JUNE 11, 2015 LIBRARY – CONVERT TO PACKAGE/COMPUTER AREA: S & I solid core door and jamb 3’-0” … Continue reading
Posted in Construction & 50 & 40 Year Recertifications
Tagged capital, construction, Entry Area, Lobby, Main Entry, Project
2 Comments
Voices of Aquarius May 28 2015
Aquarius Website Administrator of the official site: Aquariuscondo.net – email bulletin to all users, emailed 5/28/2015 at 10:32am: Many residents have reacted to this “Voices of Aquarius.” Their reactions are at the end of the message. Voices … Continue reading
Posted in Construction & 50 & 40 Year Recertifications
Tagged 2015, assessment, construction, Entry Area, improvement, Lobby, permits, Project, Valet, valet deck, voices, voices of aquarius
2 Comments
Report on Valet Deck Project May 26, 2015 1 of 2
Report on Valet Deck Project May 26, 2015 1 of 2 THE VALET DECK PROJECT On April 24, 2015, a change order (#20) was signed with CSI to act as the general contractor for the … Continue reading
Report on Valet Deck Project May 26, 2015 2 of 2
Valet Deck Project: Schedule and Logistical Plan May 26, 2015 2 of 2 .o0o.o0o.o0o.