What is going on at Aquarius – Report March 24, 2016

What is going on at Aquarius – Report March 24, 2016   Victor Rocha This is a progress report regarding the valet deck and the lobby. As you can see, the lobby is almost completely finished. The bathrooms need to … Continue reading

Posted in Board of Directors | Tagged , , , , , | Leave a comment

An Assessment of Current Projects Undertaken by the Aquarius Condo. Association

An Assessment of Current Projects Undertaken by the Aquarius Condo. Association by  Bhagwan (Buck) Gupta   with contributions of Victor Rocha. Both are candidates for the Board of 2016.  Their electoral information sheets can be seen by clicking their names. New TABS will … Continue reading

Posted in Board of Directors, Construction & 40 Year Inspection | Tagged , , , , , , , , , , , | Leave a comment

Aquarius Lobby was going to be ready by Christmas – it is NOT

Aquarius Lobby was going to be ready by Christmas – it is NOT   Since the BOD of Ilya G., Sofia F., Boris E. and Eugenia V. replaced John Y. and Joel C. in late July 2015, a curtain of … Continue reading

Posted in Construction & 40 Year Inspection, Contracts | Tagged , , , , , | 2 Comments

Aquarius Valet Deck Pavers Progress October November 2015

This gallery contains 7 photos.

Aquarius Valet Deck Pavers Progress October November 2015   Your Special Assessment money at work. The Valet Deck should be ready in a few weeks. Work started in April 2015, it should be done in December.  The initial schedule was … Continue reading

More Galleries | Tagged , , , , , , , | 2 Comments

ACG Update on Projects in Progress at Aquarius Condo. Ass. 9-25-2015

ACG Update on Projects in Progress at Aquarius Condominium Association   ACG – Engineering Services Inc. September 25, 2015. To: Board of Directors Aquarius Condominium Association, Inc. 2751 South Ocean Drive Hollywood, FL 33019 Re: Project up date ABSTRACT: As … Continue reading

Posted in Construction & 40 Year Inspection, Contracts | Tagged , , , , , , , , , , | Leave a comment

Valet Deck Progress – September 22 Pictures

Valet Deck  Progress  –  September 22 Pictures   The Valet Deck work advances. Now Phases 2, 3, 4 and 5 get waterproof protection. Phase Two of Valet Deck waterproof work. Waterproofing in progress. Phase 3 getting ready to be waterproofed. … Continue reading

Posted in Amenities, Construction & 40 Year Inspection, Pictures | Tagged , , , , , , , , , , , | Leave a comment

Delinquency Collection Procedure and amounts due September 1st. 2015

 Aquarius Condominium Association Delinquency Collection Procedure This announcement was posted by the Board of Directors August 21, 2015.   At the bottom of this post it is the value of installment due September and destination of this 2015 Special Assessment. Two … Continue reading

Posted in Board of Directors, Construction & 40 Year Inspection, Finance | Tagged , , , , , , , , , , , , , | Leave a comment

2015 Assessment – New Installment Due September 1st. Check your contribution

Aquarius   2015 Assessment – New Installment Due: September 1st. Check the amount of your contribution What is the destination of these 4 million dollars? Verify, bellow, the purpose of the Special Assessment of 2015.   2015 Aquarius Condominium Association, … Continue reading

Posted in Board of Directors, Construction & 40 Year Inspection, Finance | Tagged , , , , , , , , , , , , , , , , | Leave a comment

CSI Change Order # 21 August 13, 2015

  CSI Change Order #21 Date: 8/13/2015   CSI Change Order #21 has been signed on 08-13-2015.     Some work was added and some other cancelled. Resulted in the minor overall price change – reduction by $6,125.00. Date of substantial … Continue reading

Posted in Construction & 40 Year Inspection | Tagged , , , , , , , , , , , | Leave a comment