ACG Update on Projects in Progress at Aquarius Condo. Ass. 9-25-2015

aquarius51

ACG Update on Projects in Progress at Aquarius Condominium Association

 

2015 ACG LogoACG – Engineering Services Inc.

September 25, 2015.

To: Board of Directors Aquarius Condominium Association, Inc. 2751 South Ocean Drive Hollywood, FL 33019
Re: Project up date

ABSTRACT:

As per the Board’s request, we have prepared a project update on the different phases and projects in progress at the Aquarius Condominium. The following are the updates until September 25, 2015:

West Pool Upper Deck:

The contractor has finished all the interior finishes. They have called for final inspection on electrical and plumbing today. The roof has not been finished due to rain, but should take no more than two days to be finalized. Hollywood stone has been contacted to be on site as soon as possible to call for final inspection early next week.
The pool company has finished all the interior work. They were going to start filling the pool yesterday and they had called for final inspection on plumbing and electrical. Once all the pavers are set by Hollywood Stone they will call for final inspection.

The contractor has finished all the interior finishes. They have called for final inspection on electrical and plumbing today. The roof has not been finished due to rain, but should take no more than two days to be finalized. Hollywood stone has been contacted to be on site as soon as possible to call for final inspection early next week.
The pool company has finished all the interior work. They were going to start filling the pool yesterday and they had called for final inspection on plumbing and electrical. Once all the pavers are set by Hollywood Stone they will call for final inspection.

Lobby Deck (Valet Deck)

Phase I : No work has been done on this area last week.

Phases: II, III, and IV:

The contractor has applied the waterproofing membrane and will water test the area on Friday September 25, 2015. The water test will last 24 hours. Next week all the curbs will be formed and placed. The contractor has scheduled paver installation to start October 7, 2015. The manager will be notified today that the stone and the soil for the two front planters should be delivered in the next two weeks.
After meeting and agreeing with the contractor these are the phase percentages of completion:

  • Phase I        98%
  • Phase II       85%
  • Phase III     85%
  • Phase IV     85%
  • Bathroom and Shower      98%

Please call me should you have any questions or require further clarification.
Respectfully,
Andres Caicedo,  President

ACG   1335 St. Tropez Circle Unit 107, Weston, Florida 33328 –

Ph: 954.778,5211 – Fax: 754.816.5664 – http://www.acg-eng.com – COA#29940

.o0o.

Advertisements
This entry was posted in Construction & 40 Year Inspection, Contracts and tagged , , , , , , , , , , . Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s