A Note from the Aquarius Board Treasurer January 15, 2017

AQUARIUS-3D logo A Note from the Aquarius Board Treasurer

Sunday, January 15, 2017

 

Board  Treasurer Comments on the Latest Propaganda by Opposition

 

Good Day Aquarians! It is another Beautiful Day!

 

Yesterday, the opposition sent out another missive accusing the current board of lying to you about the current need to complete the 40-year Re-Certification. It is the same false narrative and rhetoric that they have been spewing for weeks. These are the people who have gone a long way towards causing the unnecessary decay to our buildings by using band-aid approaches, failing to do the proper maintenance of the building, doing illegal work without the proper permits to assure that the work is being done according to South Florida Building Code Requirements, wasting the Trump money by using it to defray maintenance costs, failing to close out permits that were obtained in order to do work and the list goes on. These folks, some of which are running for the board, are telling you that there is nothing wrong with the building and that the balconies are fine. 25 out of 26 concrete core samples failed the compressive strength tests. The report from Batista that they allude to was based upon a cursory visual inspection by that engineer who only spent a few hours at Aquarius and he concluded, based upon what he could see that the balconies were in need of repair. He did not do the core samples so he had no way of knowing the enormity of the concrete failure rate, which was subsequently supported by the findings of an independent lab, RAS.  Based upon such a high failure rate, it is actually cheaper to remove and replace the balconies than to patch them, as the labor rate would exponentially increase the price. Moreover, we would be doing it again in 10 years when the 50-year certification is due, and the un-repaired concrete would have continued to deteriorate and would have to be repaired again. IT IS THE OPPOSITION THAT IS LYING TO YOU.

The current Board did not hand-pick the engineering firm. As you may recall, we had several presentations to our membership of at least 6 highly competent engineering firms who specialize in concrete restoration work. There may be only 10 firms in the area that do that. 6 chose to participate. Based upon their presentations and based upon the bids, your board selected Hillman. The scope of work was not defined by Hillman. The scope of work is defined by the condition of the building that your previous boards allowed to deteriorate. Remember as a small example, our Aquarius Buildings have not been painted in at least 10 years? Is that responsible stewardship of such a precious jewel on the sea? I’m going to with NO on that!! ANOTHER LIE BY THE OPPOSITION.

This Board is NOT misleading the membership with regard to any aspect of the 40-year certification. The current board is the most transparent and informative board that this member has ever seen. We have advised the membership through monthly board meetings, weekly construction meetings, presentations by engineers and contractors and notices posted in conspicuous places as to everything this Board has done. None of the other candidates who are currently running against this Board, especially those who have served before have ever accomplished as much as this Board and performed with such utter transparency while keeping the membership fully informed of its activities and decisions. The basic reconstruction has to be done. There is no choice about that. If the membership wants the added enhancements, which will cost approximately 8-9% more, they will certainly have a right to vote on the enhancements, which will not be done unless two-thirds of the membership approves it. However, as illustrated by price comparisons of recent sales of beach condos who have added glass balconies and other improvements, the price per square foot of Aquarius should go up between 50-60%. This is your choice. THIS IS PROVEN BY RESEARCH OF RECENT CONDO SALES ON HOLLYWOOD BEACH. CHECK WITH BROWARD COUNTY PROPERTY APPRAISER’S OFFICE.

The opposition letter further goes on to mislead our membership by maligning the current board which has worked in good faith for the betterment of our community. The project will last 2 years, not 5 years. There are penalty clauses in the construction contract to prevent that. YET ANOTHER HUGE LIE BY THE OPPOSITION.

The project will not cost 30% more with overruns and changes. This is what previous boards did. The contracts have been designed and the engineers are in place to ensure that there are not changes which increase costs, in fact, the contract is designed in such way as to be over-inclusive. Consequently, our hope is that if any changes need to be made, these changes would scale down the work and result in cost decreases. THAT ONE WAS A WHOPPER, ONCE AGAIN UNSUPPORTED BY ANY FACTS.

Your units will be habitable. However, there will be some inconvenience. What the opposition appears to be proposing is, Let’s not do the 40-year Re-Certification which is required by law so that “I” will not be inconvenienced. This is a very self-centered and selfish point of view. A COMPLETE FABRICATION AND SCARE TACTIC.

The price of your unit will increase by 50-60% with the enhancements. The value of your unit will not decrease!! Talk about using scare tactics. At least try to come up with some support for the negative argument. Once again, this is a false narrative and nothing but propaganda that is unsupported by any fact.

The structural integrity of the building will not be diminished. The Structural engineers who have great insurance and are putting their licenses on the line have done this multiple times over the last 40 years and there has not been one report of finishing the structural integrity of a building. WHO IS LYING? THE OPPOSITION.

The majority of the necessary repairs are not elective. They are mandated by Florida law and the South Florida Building Code. Actually the Board owes a Fiduciary Responsibility to the membership to perform the repairs or replacements necessary to abide by the law. ONLY 8 to 9% of the costs, if approved by the membership, are for electives. At least 10 to 10.5 Million are required for the basic 40 year Certification. YET ANOTHER LIE BY THE OPPOSITION UNSUPPORTED BY ANY FACTS.

Victor E. Rocha, Treasurer of Board of Directors of Aquarius

 

.o0o.

 

Posted in Board of Directors, Construction & 50 & 40 Year Recertifications | Tagged , , , , , , , | Leave a comment

Letter from Aquarius Owner Paul Wilk January 15, 2017

LOGO LOVELetter from Aquarius Owner Paul Wilk   January 15, 2017

 

I would like to take this opportunity to say “Thank You ” to the current Board of Directors of The Aquarius Condo Association for their due diligence & efforts to bring the Aquarius back from the rubbles of the past to a bright & new potential future. This can only be achieved by hard work, & unselfishly giving up personal time & energy of each & every Board member to work diligently towards the mutual goal of making the “Aquarius Great Again.” I am kindly asking every unit owner to look deep in their minds & souls to re-elect the current Board Members. We have come so far & yet have so much farther to go.

However, the time, money & effort will surely be rewarded many times over. Please do not be shortsighted & think about the assessment as a negative, instead realize it’s the beginning of a bright new future for all of us at the Beautiful Aquarius.The pot of gold is there at the end of the rainbow to all that have the foresight & vision of the future.

Please choose wisely as this may be the most important financial decision you will make in 2017.

Thank you,

Kind regards,

Paul Wilk,   204-N

.o0o.

Posted in Uncategorized | Leave a comment

Be Careful with your vote for the Board of Directors

LOGO BLUEBe Careful with your vote for the Board of Directors

The 2017 Board of Directors election is only days away.   As unit owners we  have the responsibility and the great privilege of electing the next Board of Directors of Aquarius.

The election ballots were mailed to all the unit owners and must be handled with care in order to be counted. Please secure your vote by making sure that the ballot is received in the management office by your hand only.  You must deliver your ballot to the office in person. If you are unable to do so, then your ballot may be delivered through a proxy you designate in writing or by U.S. mail from the secondary address listed with the management office.  Make sure that your vote counts by adhering to this simple but very important rule.

Election day is January 17, 2017.  Make your vote count.   Follow the rules!

Judith Ort, Member of the Board of Directors of Aquarius

Posted in Board of Directors | Tagged , , , , , | 1 Comment

Message from the President of the Board of Aquarius

 AQUARIUS-3D logoMessage from the President of the Board

January 13, 2017

Dear Unit Owners,

Last night, your Board took the first step forward by securing a loan from the Bank, as well as passing a motion to assess ourselves to provide funding to pay off the loan.

You heard from some owners promising you a free lunch.  A question was raised as to why we do not have a signed contract to complete the project.  It is well known that a contractor is never hired without having the money to pay for the services to be rendered.

Your current Board is not taking your support for granted.  We must proceed in an orderly fashion.  We are currently in the process of negotiating a contract with the final unit prices for identified scope of work to include all enhancements.  It is much easier to reduce the scope of work and corresponding costs associated with it, then to add items with change orders for higher prices.  Once the unit owners vote and approve the enhancements to have our property brought up to date, we will have a safe and enticing place call “home” and protect our investment for years to come.

At this time, we have the opportunity to elect Board members who would carry out the necessary work to complete the project in a timely fashion without making false promises, or go back to a Board who has not delivered in the past and would only serve the interest of selected few.

It is your choice.

Bhagwan (Buck) Gupta

.o0o.

Posted in Board of Directors, Construction & 50 & 40 Year Recertifications | Tagged , , , , , , , , | Leave a comment

Facts about the balconies of Aquarius

Logo blue girlFacts about the balconies of Aquarius

 

It seems the questions about the need to replace the Aquarius Condo keep popping up.

Not the recent reports from ACG, Baptista and Hillman seem good enough. It is also important to point out that since 2009 we have had several other studies all point out the need to immediate address the balconies. This is just a sample of studies, evaluations, and professional opinions. The Aquarius Condominium pays for all this but it fails to act.

Click here for ACG 2014 report. The cover letter is a fair warning.

Click here for Gregorio Batista Structural Report 2015-2016. Many areas require immediate attention. * seen note on bottom

Click here for Hillman report 2016  – please be patient comprehensive report downloads slowly.

Click here for Concrete Compression Resistance Test of 26 balconies

Click here for original specifications of Aquarius Building construction of 1972 with a letter from Property Manager to Owner challenging facts. Facts about the Aquarius Balconies.

It is also of value to review the 2015 balconies repair effort. A contract with the total value of about $90.000 (nine thousand dollars) had been signed in late 2014. The scope was to repair about 36 balconies that required urgent attention. After some of the target for repair had to be totally replaced the work was suspended by the 2015 Board.  Bottom line: of the 36 balconies only 4 were fixed, some of them completely replaced and the Aquarius Condo had spent half of the budgeted allowance for this contract.

Should we travel the same road again? When the original concrete resistance should be of 4000 psi and 25 out 26 balconies show a resistance of under 1900 psi?

Another interesting question is: Why spend money on partial repairs joining 44 years old decrepit concrete with new concrete? The resistance of the old concrete is bellow code. Even if it is apparently good there is no guarantee that in two or three-year it will require attention again.

The time to act is now. Without your support nothing will be done.

Insanity: doing the same thing over and over again and expecting different results.                      Albert Einstein
.o0o.

Posted in Construction & 50 & 40 Year Recertifications | Tagged , , , , | Leave a comment

Balconies Ready to Collapse – Paul Wilk

LOGO ABalconies Ready to Collapse

Thank you to all of the current Board Members & other concerned residents of the Aquarius Condo for finally taking a positive stand & working towards actually doing what is badly needed to keep the Aquarius from the real possibility of being condemned & declared unlivable by the Broward Country Building Inspectors.

You can see by the pictures that the balcony above me is unsafe & ready to fall down. Notice the rusted rebar throughout. If we as a community do not stand together & approve the assessment & re-elect the current board there will surely be consequences that will cause the value of all of our units to continue to drastically decline.

However, if we can all find the strength & courage to move forward then we all will reap the benefits of an updated beautiful building to enjoy for many years as well as a tremendous financial increase in value & equity. How would you like to pay $50K to get back $150K? Sounds like a no-brainer to me. That is the reality of moving forward on the enhanced upgraded renovation with the new T-Shaped pool, glass balconies, BBQ area & all the other goodies that come with only a 10% additional increase. The future of the Aquarius is in your hands so please choose wisely.

That is the reality of moving forward on the enhanced upgraded renovation with the new T-Shaped pool , glass balconies, BBQ area & all the other goodies that come with only a 10% additional increase. The future of the Aquarius is in your hands so please choose wisely.
Kind regards,

Paul Wilk,  204 N

ready-to-collapse-2

.ready-to-collapse-1
.o0o.

Posted in Construction & 50 & 40 Year Recertifications, Pictures | Tagged , , , , , , , , | 1 Comment

Video Clips That Deserve Attention – Aquarius in Danger

Logo blue girlVideo Clips That Deserve Attention – Aquarius in Danger

We have met the enemy and he is us

Listen what some owners said in 2015. None of their predictions became reality. The same doomsdays activity is back. Who do you want to believe in? The several engineerings studies that recommend immediate action?  Or the voice of  “save now” and pay later the triple or even more?

We have engineering evaluations of the precarious situation of the building that go back since 2009.

Click here to see owners destroying the value of your investment as an Aquarius owner.

https://aquariusuno.com/2015/06/18/tv-channel-10-visits-aquarius-condo-broadcasted-june-17-2015/ or click here

Do you want to have concrete falling on your family? On your guests? On your vehicle? Should you side with the band-aid approach? Or should we do the right thing? Check this other video of concrete falling from the balconies.

https://aquariusuno.com/2016/06/20/large-debris-falling-from-7th-floor-damages-car-june-18-2016/      or click  HERE

Is it time to do something new and right or it is time to keep the same thing over and over and expect different results? Where procrastination has taken us?

.o0o.

 

Posted in Construction & 50 & 40 Year Recertifications, News from Around and Beyond, Pictures | Tagged , , , , , , , , , , | Leave a comment

Should Aquarius have Glass Balconies?

LOGO AShould Aquarius have Glass Balconies?

 

An interesting study was conducted by our neighbor Scot Bennet. The focal point of the study is: do glass balconies add any value to the property?

The evidence seems to be very strong. It adds considerable value. It is a very wise investment even if the existing balconies railings did not need replacement. Aquarius railings need replacement. Many are out of code and require eyesore plastic

Aquarius railings need replacement. Many are out of code. There are at least four distinct types of the metal picket railings in place. Some railings require eyesore plastic trellises to avoid babies and pets to fall down. They are very unsafe.

The bottom line is that the replacement is needed. The cost to put new picket metal railings is a little less than the glass railings. The tables prepared by Scot Bennet are an eye opener.

2017-01-03-sale-price-analysis-balconies

2017-01-03-sale-price-analysis-balconies2
January 2017

.o0o.

Posted in Construction & 50 & 40 Year Recertifications, Finance | Tagged , , , , , | 1 Comment

Suggested Guidelines for the next (2017) BOD of Aquarius

Aquarius logo

 Suggested Guidelines for the next (2017) BOD of Aquarius

This document was prepared by a couple of concerned owners
 that do not agree with the plans proposed by the Board of Directors
 of Aquarius. 
It received an immediate response from Zina Bluband. 
It is important to read both pieces - 
Zina's and Sam's to have a balanced view. 
Zina's reponse follows the Schmuter's piece

Purpose:

This strategy is driven by the desire to unify our community for efficiently achieving the common goal to make Aquarius “good again”. It is suggested for the next BOD, whoever is elected.

 

  1.     Fire Hillman Engineering as a company having a conflict of interest with the community. Hire another engineering company with a fixed pay. Let them re-evaluate Hillman’s conclusions.
  2.     Set the upper-level ceiling as $5,000,000 for the balconies in the 40-yr Project, plus the glass railing upgrade for additional $500,000.
  3.     Appoint the Balcony Construction Committee from the Owners experienced in construction: (like Roman Kisler , Edward Khmelevsky, Ilya Sibula, Boris Eydelnant, Zina Blueband , maybe some more …)   with the task to define the Balcony Fixing Strategy that covers all the balconies, with repair and/or     replacement, whatever is efficiently applicable.
  4.        Plan fixing East Deck and the existing East Pool for the limit of  $2,500,000 (remember, the larger in size West Deck with totally ruined West Pool were done  within $2 millions)
  5.     For another $2,000,000 select  important remaining task(s) (perhaps, elevators)
    Thus, the overall 40 yr Project must be contained within the ceiling of $10 million.

 

Conclusion:

The funds and the limits suggested here, are still very substantial. Just compare with the money so far spent on our other Decks and Lobby. Or compare wth money spent by other buildings (e.g. Wave assessed $12 mils, but they have 567 apartments, and we have under 270).

We must not exceed the limits.

Just need to see if the above limits can further accommodate some other remaining jobs (like hallways).

Samson Schmuter, 1101N  via eMail and  Zoya Schmuter, via telephone.


Zina Bluband response:

 

1) How many engineering companies you have to pay for to confirm obvious?  Waste of our money again.

2) The cost to fix balconies to comply with 40-year certification requirements cannot be based on wishful thinking, only on the engineering estimate.

3) As the owner, I would like the professional opinion on the scope of work and the process to complete it. It is very presumptios to even think the committee members are qualified to make such an important decisions for all owners.

As a last remark… Pretty tired of this exercise in a creativity from the people who obviously have an inflated opinion about their capabilities and qualifications.

Zina Bluband, Vice-Chair of the Aquarius Construction Committee for many years. Zina has been an active and assiduous participant of several efforts to bring Aquarius back  to the Broward County Construction Code full complaince.

.o0o.

Posted in Uncategorized | Leave a comment

Where Are the Engineering Evaluations of Aquarius?

LOGO SILHOUETTEWhere Are the Engineering Evaluations of Aquarius?

There is a growing interest for the report from Hillman Engineering that indicates the work required to make the Aquarius property fully recertified according to the specifications of Broward County for buildings at their 40 year anniversary.

The full report is available by clicking here.

Please be patient it is a document of more than 23 MB and the download will take some time.

It is also of great interest to see the report prepared in 2014 by another Engineering firm. Click  HERE.

At this report ACG, the firm hired and paid for by the owners of Aquarius, made recommendations indicating the urgency of the repairs. Unfortunately, it was one of the several reports ordered and paid for by Aquarius that are sent to the archives with no action.

At the present time action is going to take place. It is not healthy to postpone anymore. The procrastination since 2009 can not continue. It is time to act.

Please support what should have been done several years ago for a fraction of the cost that is now necessary. To do it later will be more onerous and we may have the Broward County taking over the building and doing the work in their schedule with their cost. To follow the law represents savings, our schedule, our control, our taste for any change. Not bureaucrats from the County  just doing their job that is to keep the structure safe.

.o0o.

 

 

Posted in Committees, Construction & 50 & 40 Year Recertifications | Tagged , , , , , | Leave a comment