Aquarius Beach Access – NO STAIRS!
Aquarius Beach Access – NO MORE STAIRS! With the construction project going on the Aquarius access to the Hollywood beach had to change. There was the need to find a temporary (hopefully permanent) alternative for the beach goers. At … Continue reading
Aquarius 40 Year Re Certification Project – 90 day Schedule
Aquarius 40 Year Re Certification Project – 90 day Schedule Preliminary Schedule subject to change ID Task Name Duration Start Date 1 AQUARIUS CONDOMIINIUM 2 Contract Signed 0 days Mon 1/16/17 3 Master Restoration Permit Processing 66 days Tue 2/7/17 … Continue reading