Where is the East Deck Aquarius Swimming Pool?
The demolition of the Aquarius East Deck. With the target date to have all South Tower Balconies and the East Deck demolished by the end of August 2017 (if the weather helps), the work has been going on is brisk pace.
The noise and the dust are a problem but we all know that the results are going to be very good.
About half of the Balconies of the South Tower have been demolished. When this step is complete next job is the reinforcement of the steel bars and new concrete that resists a pressure of 6 ton. Right now the old balconies had a dangerous concrete under the compression ratio of 2 ton.
For the residents that are not in the property some pictures give an idea of the progress of the 40 Re-Cert progress.

August 5

August 3

August 2
.o0o.