News on the Gym Bathrooms from the desk of the President

LOGO WATERNews on the Gym Bathrooms from the desk of the President

 

Finally today, after 10 working days of plumbing leak repairs, changing  PVC pipes to cast iron, and other changes required to meet the code, we reached a milestone by having Passed the inspection.

We were not able to call for a rough in inspection to close the walls, start water proofing of various areas and progressing with any type of tile work thus far. Hopefully, now we can get the other inspection scheduled for Monday, the city inspection office is closed on Fridays.

We have already passed the mechanical and electrical inspections. We can also schedule closing of ceiling and start repair work required in the Green room.

Will keep you posted.

Buck Gupta (from the iPhone)  12-1-16

.o0o.

 

About Cecilio Augusto Berndsen

Information Technology, Management, Project Management and Public Administration are areas I am familiar with. I am also interested in photography, wine, sailing, politics, economics, and economic development.
This entry was posted in Amenities, Board of Directors, Construction & 40 Year Inspection and tagged , , , . Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s