News on the Gym Bathrooms from the desk of the President
Finally today, after 10 working days of plumbing leak repairs, changing PVC pipes to cast iron, and other changes required to meet the code, we reached a milestone by having Passed the inspection.
We were not able to call for a rough in inspection to close the walls, start water proofing of various areas and progressing with any type of tile work thus far. Hopefully, now we can get the other inspection scheduled for Monday, the city inspection office is closed on Fridays.
We have already passed the mechanical and electrical inspections. We can also schedule closing of ceiling and start repair work required in the Green room.
Will keep you posted.
Buck Gupta (from the iPhone) 12-1-16