Aquarius Condominium Valet Area
4/27/15 to 1/4/2016
CSI Project Schedule
1. General Requirements | 4/27 – 5/20 |
2. Submittals | 4/27 – 5/1 |
3. Permitting | 4/27 – 5/15 |
4. City Delay | 4/27 – 5/15 |
5. General Mobilization | 5/18 – 5/20 |
6. Demolition | 5/21 – 6/25 |
7. Concrete / EIFS / Masonry / Pavers / Sand | 5/21 – 6/18 |
8. Waterproofing Membrane | 6/5 – 6/25 |
9. Structural Repairs & Plumbing Upgrades | 5/29 – 9/28 |
10. Phase 1 | 5/29 – 6/25 |
11. Phase 2 | 6/26 – 7/24 |
12. Phase 3 | 7-27 – 8/21 |
13. Phase 4 | 8/24 – 9/21 |
14. Phase 5 | 9/22 – 9/28 |
15. Replacement Garage Entrance Gate | 6/19 – 6/25 |
16. New Concrete/Stucco Work | 9/29 – 10/19 |
17. Construction Fountain / Curbs | 9/29 – 10/19 |
18. Re-Construction South Perimeter Wall | 9/29 – 10/19 |
19. Re-Surfacing Exterior Perimeter Wall | 9/29 – 10/19 |
20. Re-Surfacing Stone Cladding | 9/29 – 10/5 |
21. Construction of New Valet Soffit | 9/29 – 10/19 |
22. Waterproofing | 10/20 – 12/16 |
23. Cold Applied WP Membrane at Paver Area / Planters | 10/20 – 12/9 |
24. Cold Applied WP Membrane at Parking Area | 12/3 – 12/16 |
25. Exterior Painting | 12/17 – 12/31 |
26. Replacement Storefront | 12/24 – 12/31 |
27. Installation Sand / Pavers / Bumpers | 12/10 – 12/31 |
28. Re-Striping Parking Area | 12/17 – 12/18 |
29. Install New Glass Railing | 12/21 – 12/23 |
30. Demobilization | 1/1/16 – 1/4/16 |
C.Berndsen 05/2015