Aquarius Valet Area Project Schedule April 2015 to January 2016

aquarius51Aquarius Condominium                           Valet Area      

4/27/15 to 1/4/2016

CSI             Project Schedule

1.      General Requirements 4/27 – 5/20
2.   Submittals 4/27 – 5/1
3.    Permitting 4/27 – 5/15
4.        City Delay 4/27 –  5/15
5.   General Mobilization 5/18 – 5/20
6.    Demolition 5/21 – 6/25
7.     Concrete / EIFS / Masonry / Pavers / Sand 5/21 – 6/18
8.     Waterproofing Membrane 6/5 – 6/25
9.      Structural Repairs & Plumbing Upgrades 5/29 – 9/28
10.  Phase 1 5/29 – 6/25
11.  Phase 2 6/26 – 7/24
12.  Phase 3 7-27 – 8/21
13.  Phase 4 8/24 – 9/21
14.  Phase 5 9/22 – 9/28
15.  Replacement Garage Entrance Gate 6/19 – 6/25
16.                New Concrete/Stucco Work 9/29 –  10/19
17. Construction Fountain / Curbs 9/29 – 10/19
18.  Re-Construction South Perimeter Wall 9/29 – 10/19
19.  Re-Surfacing Exterior Perimeter Wall 9/29 – 10/19
20.  Re-Surfacing Stone Cladding 9/29 – 10/5
21.  Construction of New Valet Soffit 9/29 – 10/19
22. Waterproofing 10/20 – 12/16
23.  Cold Applied WP Membrane at Paver Area / Planters 10/20 – 12/9
24.  Cold Applied WP Membrane at Parking Area 12/3 – 12/16
25.  Exterior Painting 12/17 – 12/31
26.  Replacement Storefront 12/24 – 12/31
27.  Installation Sand / Pavers / Bumpers 12/10 – 12/31
28.  Re-Striping Parking Area 12/17 – 12/18
29.  Install New Glass Railing 12/21 – 12/23
30.  Demobilization 1/1/16 – 1/4/16

C.Berndsen 05/2015

This entry was posted in Committees, Construction & 40 Year Inspection and tagged , , , , , , , , , , . Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s